IAEA's latest update :
" Japanese authorities today announced a number of developments at Fukushima Daiichi nuclear power plant, where reactor cooling systems were disabled following the massive earthquake and tsunami on 11 March.
At Units 1, 2, 3, and 4, workers have advanced the restoration of off-site electricity, and the lights are working in Unit 3's main control room.
Black smoke was seen emerging from the Unit 3 reactor building, spurring the temporary evacuation of workers from Units 3 and 4. The emission of smoke has now decreased significantly.
Crews continued today to use a concrete pump truck to deliver high volumes of water into the Unit 4 spent fuel pool, where there are concerns of inadequate water coverage over the fuel assemblies.
At Units 5 and 6, workers have successfully restored off-site power to the reactor, which had previously reached a safe, cold shutdown status."